Gashco – Gatwick Office Fit-Out

Creating a Modern, Functional Workspace

Client: Gashco
Location: Gatwick
Project Type: Full Office Fit-Out
Start Date: 9th October 2024
Completion Date: 1st November 2024

The Brief

Gashco needed a comprehensive office transformation at their Gatwick site, including the creation of modern office space, a kitchenette, WC facilities, and a separate storage area. The project required a full-scale fit-out to meet their operational needs, ensuring the space was functional, energy-efficient, and compliant with all building regulations.

Presence & Co. was responsible for delivering a high-specification interior, including mechanical, electrical, and HVAC installations, as well as fire safety and access control solutions.

Our Approach

Workspace Design & Construction

  • Installed new stud partition walls, fully insulated and finished with high-quality white emulsion paint.
  • Constructed a dedicated storage area with a sealed concrete floor.
  • Installed fire-rated doors and joinery, ensuring compliance with fire safety standards.
  • Upgraded skirting, architraves, and interior trims with a modern satin white finish.

Plumbing & Kitchenette Fit-Out

  • Installed a fully functional kitchenette, including:
    • 600mm integrated dishwasher.
    • Under-sink 10L hot water heater (2kW) for instant hot water.
    • Stainless steel sink unit with waste connections integrated into the existing foul pop-up.
  • Connected new WC facilities, ensuring compliance with Building Regulations.
  • Installed a fresh air ventilation system to improve indoor air quality.

Electrical & Lighting Installations

  • Power Supply & Distribution:
  • Installed dado and surface-mounted trunking throughout the office for efficient power distribution.
  • Integrated double socket outlets, with power supplied from an upgraded distribution board.
  • Installed networked access control systems at entry points, enhancing security.
  • Lighting & Emergency Systems:
  • Upgraded to 600×600 LED modular office lighting with emergency backup units.
  • Motion-activated lighting in WCs, meeting rooms, and storerooms.
  • Fire alarm upgrades, including new detectors and call points installed in each subdivided area.

Heating, Cooling & Ventilation

  • HVAC System Installation:
    • Designed and installed a Split DX heating & cooling system, maintaining a stable 18-24°C temperature range.
    • Positioned external condensers on North and East-facing walls to maximise efficiency.
    • Routed all pipework within ceiling voids, maintaining a seamless finish.
  • Installed humidity-controlled extraction fans in the tea point area and WCs to ensure proper ventilation.

The Result

The new Gatwick office was completed on time and within budget, delivering a modern, functional, and energy-efficient workspace for Gashco. The integration of advanced security, electrical, and HVAC systems ensured a comfortable and compliant working environment.

Scroll to Top

We deliver luxury and creative property management solutions for residential and commercial clients throughout the South East of England and nationwide.